By providing your contact information to Bell Properties, your personal information will be processed in accordance with Bell Properties's Privacy Policy. By checking the box(es) below, you expressly consent to receive marketing or promotional real estate communication from Bell Properties in the manner selected by you. For SMS text messages, message frequency varies. Message and data rates may apply. Consent is not a condition of purchase of any goods or services. You may opt out of receiving further communications from Bell Properties at any time. To opt out of receiving SMS text messages, reply STOP to unsubscribe. SMS text messaging is subject to our Terms of Use.

Thank you for your message. We will be in touch with you shortly.

A stone and ivory-sided home with a shaded porch, oak door, broad front lawn and flowering garden bed.

The Victoria Avenue Roundabout Has Been Coming Since 2019. Its Start Date Is Still an Estimate.

The roundabout planned for Creek Meadows Boulevard and Victoria Avenue first went into College Station's capital budget in fiscal year 2019, with an original budget of $3.62 million. Its budget is now $4.3 million. The plan now covers one roundabout instead of two. The most recent public estimate puts the start of construction "toward the end of 2026 or the start of 2027," a window that opens within the next few months.

That estimate deserves a careful read. The city's own budget expected construction spending to begin a year earlier, and as of mid-October 2026 we have not found a construction contract award, a contractor or a detour plan in the public record. Taken together, the paper trail suggests the safest planning assumption for anyone who drives Victoria daily: the work is coming, the date is soft, and it may run into a much bigger project on Wellborn Road.

What the city has actually committed to build

The project is listed in College Station's FY2025–26 capital budget as "Victoria Roundabout and Sidewalks," project number ST1901, managed by Public Works and funded through Certificates of Obligation. The scope is specific:

  • A concrete roundabout replacing the existing asphalt at Victoria and Creek Meadows, with curb and gutter, underground storm sewer, sidewalks and street lighting
  • A 10-foot-wide concrete multiuse path along the south side of Victoria, running from Creek Meadows to Woodlake Drive
  • Drainage work and a water line relocation, according to the city's October 23, 2025 council meeting recap

The roundabout is single-lane. KBTX reported that it belongs to the Wellborn Road upgrades the city adopted in 2023, and that it is one of about 65 active capital projects.

A plan that got smaller as it got more expensive

The project's history explains why a late-2026 start date shouldn't be treated as firm. A city workshop presentation from December 11, 2023 sets out the contract record:

  1. June 13, 2019: City Council approves the preliminary engineering contract for $234,500.
  2. January 28, 2021: The original engineering design contract is approved for $458,400.
  3. May 26, 2022: The scope is revised. A change order closes out the first design contract, and a new design contract is approved for $182,900.
  4. December 2023: The working scope calls for concrete roundabouts at both Creek Meadows and Woodlake Drive, plus a study of whether a sidewalk on the south side of Victoria between them is feasible.

By the time the project reached the FY2025–26 budget and the October 2025 council vote, the Woodlake roundabout had dropped out of the description. One roundabout remained at Creek Meadows, and the sidewalk study had turned into a funded 10-foot path. The project went through three engineering contracts in four years. Since then the scope has narrowed and the budget has risen from $3.62 million to $4.3 million.

Why a roundabout, by the city's own numbers

The 2023 workshop made the case for roundabouts with national safety figures. A modern roundabout moves traffic one way, counterclockwise. Drivers yield on entry, and cars yield to pedestrians.

Measure Traditional four-way intersection Single-lane roundabout
Vehicle-to-vehicle conflict points 32 8
Vehicle-to-pedestrian conflict points 24 8

The same presentation cites a 62% reduction in all crashes, an 85% reduction in injury crashes and an 82% reduction in fatal and injury crashes combined where a two-way stop-controlled intersection is converted to a roundabout. Those are general figures from the city's slide deck, not a forecast for this particular intersection.

The local case comes from the street itself. In its January 2026 report, KBTX spoke with Sam Jenkins, co-owner of CrossFit SDA on Victoria. She described cars popping tires on the bumpy stretch coming off Wellborn and drivers coming through the curve at high speed. Public Works Director Emily Fisher described the project to KBTX this way:

"So with the roundabout project, there will be a sidewalk installed from Creek Meadows back to Castlegate II, so that will give access to pedestrians and bike riders. One of the benefits of the roundabout will be to slow traffic down through that area so just be careful when you're driving through it."

Fisher's wording puts the path's far end at Castlegate II. The city's budget document and council recap both name Woodlake Drive as the endpoint, so the official documents are the better reference for where the concrete will stop. Jenkins told KBTX she expects the sidewalk to help, since her gym's workouts include a lot of running.

The vote to condemn the right-of-way

The most recent council action on the project that we found came at 9:40 p.m. on October 23, 2025. City Council voted 4–2 to authorize eminent domain to acquire right-of-way for the roundabout. Councilmen Bob Yancy and David White voted against.

The resolution covered four tracts. Two were privately owned right-of-way strips, each appraised at under $10,000, where the city and the owners had not agreed on value. The other two were held by Creek Meadows Partners and tied to adjacent residential development. At that meeting, $601,991 of the $4.3 million budget had been spent or committed, leaving almost $3.7 million. Most of the money was still unspent, which points to most of the work still ahead.

Reading the schedule the city wrote for itself

The FY2025–26 capital budget lays out year-by-year forecasts for ST1901. It projected $1,000,000 in construction spending in fiscal 2025 and $1,350,359 in fiscal 2026. That budget year ran from October 1, 2025 through September 30, 2026.

Both of those years have now ended. Meanwhile, the city was still moving to acquire right-of-way in October 2025, and in January 2026 Fisher gave KBTX a start window of late 2026 or early 2027, with construction taking about a year. We found no construction contract award, bid amount, contractor or published detour plan for the project through mid-October 2026. A city capital projects update presented to council on June 25, 2026 covered other projects and did not include Victoria.

The money is budgeted and eminent domain proceedings were authorized. Each time the city has put a timeline on paper, the actual start has come later than planned. If the early-2027 end of Fisher's window holds and the build takes the full year she described, the roundabout would be under construction for most of 2027.

Then Wellborn Road gets its turn

That brings in the second project on the same corridor. TxDOT's proposed FM 2154 widening covers Wellborn Road from SH 40/William D. Fitch Parkway to Greens Prairie Road. The plan adds four lanes, a raised median, turn lanes and a shared-use path on the east side.

TxDOT's posted anticipated schedule targets environmental clearance in late 2026 and the start of construction in summer 2027. It is a planning document with no publication date visible, so it is a target, not a commitment.

Here is what the two estimates add up to. If both hold, Victoria Avenue could be in its roundabout build at the same time TxDOT starts work on Wellborn. If either slips, the overlap moves. Either way, the city's roundabout and TxDOT's widening sit on the same corridor, and 2027 is the year both agencies currently point to. For anyone in Creek Meadows whose daily route runs from Victoria to Wellborn, the realistic expectation is a stretch of construction on the way out of the neighborhood, not a single short disruption at one intersection.

What changes once the cones come down

The finished product changes two things. Drivers coming off Wellborn will meet a single-lane roundabout at Creek Meadows Boulevard instead of the current approach, and the city's stated goal is lower speeds through that curve. Anyone on foot or a bike gets a dedicated 10-foot concrete path on the south side of Victoria between Creek Meadows and Woodlake Drive. That gives a run, a dog walk or a ride along Victoria its own lane, separate from traffic.

The next public milestone to watch for is a construction contract going to City Council. That vote will name the contractor and the price, and it will likely come with a firmer start date than anything published so far. City Council agendas and the city's "Live from City Hall" recaps on blog.cstx.gov are where that item will appear first.

At Maurey Bell Group, we manage and lease homes in south College Station, so we keep track of projects like this because construction on a neighborhood's main exit affects showings, move-in days and vendor access. If you own a home in Creek Meadows and want to know how a year of roadwork on Victoria and Wellborn could affect a sale or a lease, request a free home valuation and property management quote, and we'll walk through the timing with you.